The work done up front in preparing for the acquisition of software will help ensure that the best software package is selected.
| Step | Tools | |
|---|---|---|
| 1 | Gather and report lessons learned to date
4 Lessons learned from activities and steps of the previous phase should be gathered from key project participants. |
|
| 2 | Schedule Activities
4 Define and manage sequence of acquisition activities and timeline for each based on acquisition strategy previously defined during Initiation stage |
|
| 3 | Determine if Third Party Expert Needed
4 Evaluate internal team skills against requisite skills to identify gaps and determine level of assistance needed from an outside expert |
|
| 3a | Engage 3rd Party if Needed
4 If third party is required, competitively engage a proven, independent third party that fills the gap in skills & experience. Independence should be demonstrated by having no vested interest in the work to be awarded. |
|
| 4 | Identify Team
4 Inventory tem members needed to conduct the acquisition of software. Commence efforts to organize & recruit team. |
|
| 5 | Gather Software Related Contract Info
4 Evaluate Software License & maintenance agreement alternatives, including the Enterprise Software Initiative, GSA and other contract vehicle alternatives. |
|
| 6 | Team Kick-off
4 Hold team kick-off meeting. |
|
| 7 | Identify Potential Vendors
4 Develop initial list of software vendors through various techniques such as RFI, Web research, references and other sources |
|
| 8 | Establish Evaluation Factors Matrix
4 Establish initial list of evaluation criteria and weightings |
|
| 9 | Conduct Initial Vendor Research
4 Evaluate initial list of potential software vendors against evaluation factors defined in Step 7 above. |
|
| 10 | Determine Initial Bidders
4 Develop the list of Software Vendors you plan to send the RFP to based on previously established evaluation criteria and research |